Saturday, August 16, 2008

API Pipes as Pile Matl

Dear Mr. Zabala:

Couple of years ago, we did a number of steel pile tests (all H-piles) and developed design guidelines which are in the current AISC Seismic provisions (2005). One of the most important issues was local buckling. Although we did not do tests of pipe piles, but based on what we learned from these tests, i would give me my 2-cents on your question, hoping that others with more direct experience will jump in and contribute and specially correct me!

Here is my 2-cents:

If the pipes are with welded seams, it has to be shown that the seams will hold up under the impact during the pile-driving process. If the pipes are seamless, then you can take a look at the URL below which has comparisons of chemical composition and mechanical properties of seamless pipes made of
ASTM A53 Grade B and API-5L grades 42 to 60.

http://www.geocities.com/ferroslav/fcemmec.html (please be warned that this site has elevator music in the background!)


It seems that the API-5L Grades 46 and higher strength grades have ultimate elongation that varies from less than 17.5% to 28%. The lower end is a bit of concern in being less than 20%. If there are reliable material properties on these pipes such as mill certificates or better yet actual ASTM coupon tests, then one can compare their mechanical properties to other steel used in steel piles. You may want to ask Pile Driving Contractors Association (http://www.piledrivers.org/askpdca.php ) about their experience and how they feel about driving these piles. I have had very good experience with this group in the past. Their motto is "Driven piles are tested piles!" You may want to have 2-3 of these piles actually driven at the site and even have a lab do a pile loading test on them if you end up finding no precedence in other people using them successfully.

For seismic regions, even for non-seismic areas, if the pipe piles are filled with concrete, they will perform really well specially if seismic loads are large. Filling the piles for at least 10-20 feet from the top can make a big difference in their performance.

For local buckling issues your piles having D=12" and t=.50" makes a D/t of 24 is far less than 0.11E/Fy for applications where seismic R factor is 3 or less and even less than more stringent seismic limit of 0.044E/Fy for D/t ratio of pipes in applications with R> 3.0. My understanding is that local buckling under impact compression can occur easier than when the member is subjected to gradual application of compression load but I am not aware of any local buckling limits for compression applied under impact (high strain rate) as is the case with driven piles.

Finally, you also need to look into corrosion behavior of these piles, but, that is beyond my qualifications to comment on.

Best wishes.

Abolhassan Astaneh-Asl, Ph.D., P.E., Professor
and Consultant on Structural Engineering, Earthquake Engineering and
Protection of Buildings and Bridges against Blast and Impact
(www.ce.berkeley.edu/~astaneh)

From: milo zabala <milozabala@yahoo.com>
Subject: API Pipes as Pile Matl
To: seaint@seaint.org

--0-1922731843-1218856206=:55605
Content-Type: text/plain; charset=us-ascii

List,

Our client has extra API pipes (12" dia. x 1/2 thk) that he prefer to use as pile foundation for a pipe rack project. Building code does not list API pipes as pile material.

Any advise on the suitability or acceptability of these material for building applications.

Thanks in advance.

Milo Zabala


******* ****** ******* ******** ******* ******* ******* ***
* Read list FAQ at: http://www.seaint.org/list_FAQ.asp
*
* This email was sent to you via Structural Engineers
* Association of Southern California (SEAOSC) server. To
* subscribe (no fee) or UnSubscribe, please go to:
*
* http://www.seaint.org/sealist1.asp
*
* Questions to seaint-ad@seaint.org. Remember, any email you
* send to the list is public domain and may be re-posted
* without your permission. Make sure you visit our web
* site at: http://www.seaint.org
******* ****** ****** ****** ******* ****** ****** ********

Re: API Pipes as Pile Matl

Milo,
 
        I've used 6" pipe piles for a few miles of light pipe rack and have never had a problem.  12" seams a bit excessive; but, if the client has the material and has no better use for it, why not use it for piperack support.
 
Regards,
 
H. Daryl Richardson
----- Original Message -----
Sent: Friday, August 15, 2008 9:10 PM
Subject: API Pipes as Pile Matl

List,

Our client has extra API pipes (12" dia. x 1/2 thk) that he prefer to use as pile foundation for a pipe rack project. Building code does not list API pipes as pile material.

Any advise on the suitability or acceptability of these material for building applications.

Thanks in advance.  

Milo Zabala



Re: Anchor Studs in Concrete in Seismic

Joe
 
Yes, they are included in the Seismic load combinations. Now, CBC Chapter 19A which is much more restrictive than Chapter 19, gives some exceptions that make a lot of sense, see 1908A.1.47.
I hope that these exceptions are incorporated in the std. part of the CBC.
 
Jules
 
----- Original Message -----
Sent: Friday, August 15, 2008 10:02 AM
Subject: Anchor Studs in Concrete in Seismic

When designing embed plates with HAS's in a high seismic zone, in lieu of ductility requirements, ASCE 7-05 14.2.2.17 allows a design strength 2.5 times the factored forces.  My understanding, if correct, is that the 2.5 factor is applied to the seismic load combinations.  My question is does it also apply to DL and LL within those combinations or just the earthquake values?  Yes, No?

 

Thanks,

Joe Grill

 

 

Friday, August 15, 2008

API Pipes as Pile Matl

List,

Our client has extra API pipes (12" dia. x 1/2 thk) that he prefer to use as pile foundation for a pipe rack project. Building code does not list API pipes as pile material.

Any advise on the suitability or acceptability of these material for building applications.

Thanks in advance.  

Milo Zabala



Re: Wind load design for Photovoltaic panel installations

Yeah, I guess all these roofs that were designed for 16 PSF from the start of time
are gonna fail now, what a concept >:-o

Tarek Mokhtar, SE




Yeah, no shit. :-)

-gm
On Fri, Aug 15, 2008 at 12:46 PM, Bill Allen <T.W.Allen@cox.net> wrote:
16 PSF on a 4:12 slope?
 
Not dialed into the 2007 CBC / ASCE 7-05 I see.
 
:o)
 
T. William (Bill) Allen, S.E.
ALLEN DESIGNS
Consulting Structural Engineers
 
V (949) 248-8588 * F(949) 209-2509
-----Original Message-----
From:
sscholl2@juno.com [mailto:sscholl2@juno.com]
Sent: Friday, August 15, 2008 11:33 AM
To:
seaint@seaint.org
Subject: RE: Wind load design for Photovoltaic panel installations
 
I have entered this late but wish to learn what the problem is.
It seems to me that photovoltaic panels (which I believe weigh about 3 lbs/sq. ft.) will prohibit anyone walking on the roof (for which we design for 16psf on a 4/12 slope) and thus the load is less not more than typical design load.  Is this what is of concern?
Stan Scholl, P.E.
(someone with a very low  PE number)


____________________________________________________________
Become a pharmacy assistant. Click here to start your career now.


--  






Re: Wind load design for Photovoltaic panel installations

Yeah, no shit. :-)

-gm

On Fri, Aug 15, 2008 at 12:46 PM, Bill Allen <T.W.Allen@cox.net> wrote:

16 PSF on a 4:12 slope?

 

Not dialed into the 2007 CBC / ASCE 7-05 I see.

 

:o)

 

T. William (Bill) Allen, S.E.

ALLEN DESIGNS

Consulting Structural Engineers
 
V (949) 248-8588 F(949) 209-2509

-----Original Message-----
From: sscholl2@juno.com [mailto:sscholl2@juno.com]
Sent: Friday, August 15, 2008 11:33 AM
To: seaint@seaint.org
Subject: RE: Wind load design for Photovoltaic panel installations

 

I have entered this late but wish to learn what the problem is.

It seems to me that photovoltaic panels (which I believe weigh about 3 lbs/sq. ft.) will prohibit anyone walking on the roof (for which we design for 16psf on a 4/12 slope) and thus the load is less not more than typical design load.  Is this what is of concern?

Stan Scholl, P.E.

(someone with a very low  PE number)



____________________________________________________________
Become a pharmacy assistant. Click here to start your career now.


RE: SDC D Ordinary Moment frame connection using HSS sections

Jason and Suresh:
 
Thank you for you response.
That's correct. 
And my response is in the context of the "IBC 2006 Seismic Design Manual" where all of the structures are multistory and heavy.
Have a great weekend.

Regards


Casey (Khashayar) Hemmatyar
<khemmatyar_AT_hotmail.com>

___________________________________________________________________ 

From: Acharya, Suresh [mailto:Suresh.Acharya@ci.concord.ca.us]
Sent: Thursday, August 14, 2008 8:48 AM
To: 'seaint@seaint.org'
Subject: RE: SDC D Ordinary Moment frame connection using HSS sections

 

Casey,

Section 12.2.5.6 as referenced by footnote "h" allows OMF under certain limitations for structures in D or E. These limitations are very generous.

 

Regarding HSS, "User Note" in Section 11.1 of AISC-Seismic gives you a hint. HSS can be used.

 

Suresh Acharya, S.E.

 


 

 

From: Jason Christensen [mailto:jason@wcaeng.com]
Sent: Thursday, August 14, 2008 8:35 AM
To: seaint@seaint.org
Subject: RE: SDC D Ordinary Moment frame connection using HSS sections

 

Casey,

 

Footnote h to Table 12.2-1 refers to section 12.2.5.6 & 12.2.5.7 where both OMF and ISMF are permitted if the requirements are met.  It even mentions that OMFs are allowed in the footnote h.

 

Jason

 

From: Casey K. Hemmatyar [mailto:khemmatyar@gmail.com]
Sent: Thursday, August 14, 2008 9:32 AM
To: seaint@seaint.org
Subject: RE: SDC D Ordinary Moment frame connection using HSS sections

 

Joe:

 

No. OSMF is not permitted, period.
This is not because of HSS sections.

 

You may refer to Table 12.2-1;  item C4.
OSMF is only permitted in SDC A, B & C.
In SDC D one can only go with SMRF or if qualifies for footnote "h", may use ISMF.

Regards


Casey (Khashayar) Hemmatyar
<khemmatyar_AT_hotmail.com>

_________________________________________________________________________

From: Joseph R. Grill [mailto:jrgrill@cableone.net]
Sent: Wednesday, August 13, 2008 9:28 PM
To:
seaint@seaint.org
Subject: SDC D Ordinary Moment frame connection using HSS sections

 

Can HSS sections be used in an Ordinary Moment Frame in a SDC D.  I can't see, in the seismic design manual,  where it is specifically excluded, but I can't find any information for the HSS Beam to HSS column connection design.  It seems that it can't be done since a full pen weld is difficult if not impossible to do for a HSS beam to HSS Column face.  If there is an example out there I would love to see it.  I am doing some work for a fabricator and they are expecting HSS sections due to what is seen in the construction documents.  I have to let him know real soon if he will need to go to wide flange members.

 

Thanks for the help,

Joe Grill

 

Joseph R. Grill, PE

Verde Valley Engineering, PLLC

2220 Sky Drive

Clarkdale, AZ 86324

Ph. (928) 600-5459

Fax (928) 649-3659

email: VVEng@cableone.net

Re: Wind load design for Photovoltaic panel installations

Dennis did you talk to a panel manufacturer? I recall a U.S.A. company was wind tunnel testing that show physical connection to roof was not required in some cases. The systems just sit on roof. Reason roof penetrations can be prohibitively costly for these systems. Whether the AHJ will accept test data is another complexity.

Also I am in accordance with Stan Scholl, most if not all of these panels are not designed to be walked on.

RE: Wind load design for Photovoltaic panel installations

16 PSF on a 4:12 slope?

 

Not dialed into the 2007 CBC / ASCE 7-05 I see.

 

:o)

 

T. William (Bill) Allen, S.E.

ALLEN DESIGNS

Consulting Structural Engineers
 
V (949) 248-8588 F(949) 209-2509

-----Original Message-----
From: sscholl2@juno.com [mailto:sscholl2@juno.com]
Sent: Friday, August 15, 2008 11:33 AM
To: seaint@seaint.org
Subject: RE: Wind load design for Photovoltaic panel installations

 

I have entered this late but wish to learn what the problem is.

It seems to me that photovoltaic panels (which I believe weigh about 3 lbs/sq. ft.) will prohibit anyone walking on the roof (for which we design for 16psf on a 4/12 slope) and thus the load is less not more than typical design load.  Is this what is of concern?

Stan Scholl, P.E.

(someone with a very low  PE number)

Re: Wind load design for Photovoltaic panel installations

Not sure either, since a screw or lag at each corner is likely more than enough to stop this thing from uplifting off the main roof. (I'd be more concern about the contractor actually hitting the rafter dead center so as not to split it with the lag). Even at 50 psf, for a 4x4 panel, that's only 200 lbs at each corner uplift.

-gm



On Fri, Aug 15, 2008 at 11:32 AM, sscholl2@juno.com <sscholl2@juno.com> wrote:

I have entered this late but wish to learn what the problem is.

It seems to me that photovoltaic panels (which I believe weigh about 3 lbs/sq. ft.) will prohibit anyone walking on the roof (for which we design for 16psf on a 4/12 slope) and thus the load is less not more than typical design load.  Is this what is of concern?

Stan Scholl, P.E.

(someone with a very low  PE number)



____________________________________________________________
Become a pharmacy assistant. Click here to start your career now.


RE: Wind load design for Photovoltaic panel installations

I have entered this late but wish to learn what the problem is.

It seems to me that photovoltaic panels (which I believe weigh about 3 lbs/sq. ft.) will prohibit anyone walking on the roof (for which we design for 16psf on a 4/12 slope) and thus the load is less not more than typical design load.  Is this what is of concern?

Stan Scholl, P.E.

(someone with a very low  PE number)

RE: solar panels/ liability

Andrew,

 

I hear you.  But at the same time, I find it very difficult to turn down this work.  These people need help, and we’re the only ones who can help them.  If I explain what’s involved and they decide to go elsewhere, fine.  But I can’t bring myself to refuse it outright.  Is that what you do—a policy that you don’t touch any of this stuff?  Almost always, when the client agrees to the agenda, timeframe, money, etc, they still turn out to be bad jobs, and I would rather leave them alone, but it’s sort of a public service thing.

 

regards,

Gordon Goodell

 

 

 

Andrew Kester, PE wrote:

 

 The same I have found true for mobile home foundations, truss “engineering”, swimming pools, wood decks, pool screen enclosures, tract home reuses, etc….

 

re: solar panels/ liability

Dennis,

You came to the same conclusion I had the moment I read your post, the risk to reward ratio is not there for this type of project. The same I have found true for mobile home foundations, truss “engineering”, swimming pools, wood decks, pool screen enclosures, tract home reuses, etc…. Someone out their will stamp anything in front of them until they are busted, and I read their names in every Florida Board of PEs newsletter. For the most part clients will not pay anything resembling even a minimum wage to do this type of work.

 

 The shocking thing for me is how often their PE numbers are very low, which suggests a certain older population of engineers in FL seems to be signing away anything. For example I am 60993 and am 33, and I remember there was a guy with number like 15000 who got his license permanently revoked after stamping residential drawings for the millionth time that did not comply after having action taken against them already. I am not sure if some people are retired and just don’t care anymore, but I hate to think there are engineers willing to do this for a couple hundred bucks.

 

We just had a project involving vehicle guardrail cable system, and it was sort of pre-designed and we were trying to make it work, though it was not even close in every regard: cable size, posts, embedments, connections, etc. We were maybe 60% through the design and taking longer than what the client wanted, and out of the blue they called us and said NEVERMIND. They needed S and S dwgs that day or they would lose the project. There would have been a lot of coordination with the EOR of the main structure to make the connections for the cables work, not to mention a complete redesign of the guardrails. But some other engineer was willing to S and S what they had done to get a permit. I can only hope that even though it is not allowed, once they get a permit they will actually have a real design that works done. But our hands are clean…

 

Engineering is a business, and some people just want YES men, good to hear you are not one of them Dennis. And that is why you will hopefully have a long and fruitful career without getting brought in front of a board who is wondering why all the solar panel attachments failed during a small wind event….

 

Andrew Kester, PE

Orlando, FL

 

Anchor Studs in Concrete in Seismic

When designing embed plates with HAS’s in a high seismic zone, in lieu of ductility requirements, ASCE 7-05 14.2.2.17 allows a design strength 2.5 times the factored forces.  My understanding, if correct, is that the 2.5 factor is applied to the seismic load combinations.  My question is does it also apply to DL and LL within those combinations or just the earthquake values?  Yes, No?

 

Thanks,

Joe Grill

 

 

RE: SDC D Ordinary Moment frame connection using HSS sections

Thanks Gordon, great info.

 

Mark

 


From: Gordon Goodell [mailto:GordonGoodell@harmonydesigninc.com]
Sent: Thursday, August 14, 2008 4:47 PM
To: seaint@seaint.org
Subject: RE: SDC D Ordinary Moment frame connection using HSS sections

 

Mark,

 

AWS D1.1, provision 5.10 requires removal of backing on welds that are transverse to the direction of stress, but not for welds that are parallel.  Maybe at 45º half of the backing should be removed.  Just kidding.  It is a stress concentrator and inhibits ductile behaviour, and you would not want to leave the backing in a SMF, but maybe OK for an OMF with low force levels.  But D1.1 applies to OMF.  SMFs are governed by the seismic supplement, D1.8, which is more restrictive.

 

regards,

Gordon

 

From: Mark D. Baker [mailto:shake4bake@verizon.net]
Sent: Thursday, August 14, 2008 1:40 PM
To: seaint@seaint.org
Subject: RE: SDC D Ordinary Moment frame connection using HSS sections

 

Gordon,

 

Hmmm, in the case of the V, rounding the point of V would aid in reducing stress concentration effects.

 

In the case of tension force at 45 to weld I also am interested in others comments. Could one convince himself that the tension force is resolved as simply as a couple in the plane of top and bottom of beam within column thereby staying out of weld? I guess I’d have to slow down and sketch a stress diagram through the joint to really think this through.

 

To further display my ignorance…..where is it written that backing must be removed when force is at 45 to weld?

 

MDB

 


From: Gordon Goodell [mailto:GordonGoodell@harmonydesigninc.com]
Sent: Thursday, August 14, 2008 11:18 AM
To: seaint@seaint.org
Subject: RE: SDC D Ordinary Moment frame connection using HSS sections

 

Mark,

 

If I’m understanding you correctly, cyclical tension force would be at a 45º angle to the weld, so the backing would have to be removed, which could not be accomplished.  Also, there would be a significant stress increase at the point of the V.

 

This is a really good question.  I’d be interested to know how others deal with it.

 

regards,

Gordon Goodell

 

 

 

Mark D. Baker wrote:

 

“In the situation where column meets beam and the column does not continue past beam, cut ends of column and beam at 45, backing can be installed for this joint.

 

Where column does run past beam, cut notch in column in a V shape (female end) and cut end of beam in a V shape (male end) to insert into the column notch. This joint also will be able to receive backing plates.

 

You are correct that when trying to join the beam to the column face, full pen welds are nearly impossible.”

 

 

 

RE: Wind load design for Photovoltaic panel installations

This is the point when dealing with clients who consider the engineering
requirements as a necessary evil caused by the building official or by the
engineering community who is attempting to create a market rather than
practicing the science for the protection of the public.
It does get frustrating because it is often very difficult to explain in
basic layperson's language the necessity of what we do. The only thing that
they see is that they have a product to be mounted on a house and they
cannot profit from the sale and installation of their product until the
engineer approves their work. More time than not, the potential client
believes that we need only review what they have done and then seal it with
our stamp. They will suggest that they might stop by the office, bring the
plans and expect you to wet seal it on the spot but your judgment alone.
This is compounded often by the plan technician who will only tell them that
they need the approval of a licensed engineer but will not explain what the
correction list means. Unlike our side of this coin, it is all "Greek" to
them :)

Yes, frustration is putting it mildly. In larger projects, there are more
technical minded people who understand the complexity of the work. But
working for a distributor and installer of a product could care less - they
just want the permit and the profit without the consideration or
understanding of our design processes. The issues compound matters when
there is an engineer who is behind the times and is willing to wet stamp for
a fee. Unless the damage or injury occurs, the unlicensed counter tech will
generally accept the judgment and seal of the engineer is collecting a fee
for plan stamping.

Dennis

-----Original Message-----
From: Jordan Truesdell, PE [mailto:seaint2@truesdellengineering.com]
Sent: Friday, August 15, 2008 4:17 AM
To: seaint@seaint.org
Subject: Re: Wind load design for Photovoltaic panel installations

Good point. We generally don't have plan checks of calculations here in
the mid-atlantic, so I tend to be more at leisure to use a rational
engineering process. Abandoning the obvious calculation method for a
shoe-horned procedure that may not really applicable - but will not
confuse a poorly educated code checker - must be very frustrating.

Jordan

Dennis Wish wrote:
> Jordan,
> While I thank you for the information, I think selling this method to a
> local residential building plan checker is going to raise more questions
> about compliance with what section of the code that is applicable than it
is
> worth. <snip>

******* ****** ******* ******** ******* ******* ******* ***
* Read list FAQ at: http://www.seaint.org/list_FAQ.asp
*
* This email was sent to you via Structural Engineers
* Association of Southern California (SEAOSC) server. To
* subscribe (no fee) or UnSubscribe, please go to:
*
* http://www.seaint.org/sealist1.asp
*
* Questions to seaint-ad@seaint.org. Remember, any email you
* send to the list is public domain and may be re-posted
* without your permission. Make sure you visit our web
* site at: http://www.seaint.org
******* ****** ****** ****** ******* ****** ****** ********

******* ****** ******* ******** ******* ******* ******* ***
* Read list FAQ at: http://www.seaint.org/list_FAQ.asp
*
* This email was sent to you via Structural Engineers
* Association of Southern California (SEAOSC) server. To
* subscribe (no fee) or UnSubscribe, please go to:
*
* http://www.seaint.org/sealist1.asp
*
* Questions to seaint-ad@seaint.org. Remember, any email you
* send to the list is public domain and may be re-posted
* without your permission. Make sure you visit our web
* site at: http://www.seaint.org
******* ****** ****** ****** ******* ****** ****** ********

Re: Wind load design for Photovoltaic panel installations

Good point. We generally don't have plan checks of calculations here in
the mid-atlantic, so I tend to be more at leisure to use a rational
engineering process. Abandoning the obvious calculation method for a
shoe-horned procedure that may not really applicable - but will not
confuse a poorly educated code checker - must be very frustrating.

Jordan

Dennis Wish wrote:
> Jordan,
> While I thank you for the information, I think selling this method to a
> local residential building plan checker is going to raise more questions
> about compliance with what section of the code that is applicable than it is
> worth. <snip>

******* ****** ******* ******** ******* ******* ******* ***
* Read list FAQ at: http://www.seaint.org/list_FAQ.asp
*
* This email was sent to you via Structural Engineers
* Association of Southern California (SEAOSC) server. To
* subscribe (no fee) or UnSubscribe, please go to:
*
* http://www.seaint.org/sealist1.asp
*
* Questions to seaint-ad@seaint.org. Remember, any email you
* send to the list is public domain and may be re-posted
* without your permission. Make sure you visit our web
* site at: http://www.seaint.org
******* ****** ****** ****** ******* ****** ****** ********

Thursday, August 14, 2008

RE: SDC D Ordinary Moment frame connection using HSS sections

I haven’t heard back from Joe privately on this but I suggested that he consider the MiiTek SidePlate™ moment frame and give Hardy Frame (the MiiTek company) to see if their HSS moment frames can be used for this consideration. You can check this out on their website at http://www.hardyframe.com.

 

If Brian Wehmeier, PE (Hardy Frame / MiiTek) picks this up off the SEAINT List he might have some comments to offer that can help educate us all in the possible creative use of the SidePlate™ moment frame.

 

Dennis

 

From: Joseph R. Grill [mailto:jrgrill@cableone.net]
Sent: Thursday, August 14, 2008 7:03 AM
To: seaint@seaint.org
Subject: RE: SDC D Ordinary Moment frame connection using HSS sections

 

Thank you.  The fabricator doing this is the one saying no full pen welds.  I’m not sure other detailing requirements for a SDC D can be made with the HSS sections.  I can’t find any examples relating.  This is relating to my little stair tower problem that I fell into (wishing I hadn’t now).  The seismic issues just came up yesterday and do make a mess of the process considering the small scope and smaller time frame.

 

If there are any seismic Gurus out there, do you think a stair tower which consists of a moment frame can be considered a non-building structure?  If so, can a person use the “all other structures” category with an R=1.25, and if so does that allow a design without all the seismic detailing issues?

 

Any help

 

Joe

 

From: Conrad Harrison [mailto:sch.tectonic@bigpond.com]
Sent: Thursday, August 14, 2008 12:05 AM
To: seaint@seaint.org
Subject: RE: SDC D Ordinary Moment frame connection using HSS sections

 

I wouldn’t say it was impossible it just has to be from one side, using backing plates: which may still be the preferred practice if using wide flange beams especially if they lack depth. The Seismic requirements I cannot comment on.

 

Regards

Conrad Harrison

B.Tech (mfg & mech), MIIE, gradTIEAust

mailto:sch.tectonic@bigpond.com

Adelaide

South Australia


From: Joseph R. Grill [mailto:jrgrill@cableone.net]
Sent: Thursday, 14 August 2008 13:58
To: seaint@seaint.org
Subject: SDC D Ordinary Moment frame connection using HSS sections

 

Can HSS sections be used in an Ordinary Moment Frame in a SDC D.  I can’t see, in the seismic design manual,  where it is specifically excluded, but I can’t find any information for the HSS Beam to HSS column connection design.  It seems that it can’t be done since a full pen weld is difficult if not impossible to do for a HSS beam to HSS Column face.  If there is an example out there I would love to see it.  I am doing some work for a fabricator and they are expecting HSS sections due to what is seen in the construction documents.  I have to let him know real soon if he will need to go to wide flange members.

 

Thanks for the help,

Joe Grill

 

Joseph R. Grill, PE

Verde Valley Engineering, PLLC

2220 Sky Drive

Clarkdale, AZ 86324

Ph. (928) 600-5459

Fax (928) 649-3659

email: VVEng@cableone.net

 

RE: Wind load design for Photovoltaic panel installations

Robert,

Thank you. Permission granted.


Regards
Conrad Harrison
B.Tech (mfg & mech), MIIE, gradTIEAust
mailto:sch.tectonic@bigpond.com
Adelaide
South Australia

******* ****** ******* ******** ******* ******* ******* ***
* Read list FAQ at: http://www.seaint.org/list_FAQ.asp
*
* This email was sent to you via Structural Engineers
* Association of Southern California (SEAOSC) server. To
* subscribe (no fee) or UnSubscribe, please go to:
*
* http://www.seaint.org/sealist1.asp
*
* Questions to seaint-ad@seaint.org. Remember, any email you
* send to the list is public domain and may be re-posted
* without your permission. Make sure you visit our web
* site at: http://www.seaint.org
******* ****** ****** ****** ******* ****** ****** ********

RE: Wind load design for Photovoltaic panel installations

Conrad,
I can't argue your points - they are well stated and while I would agree
with you, it is a moot point as the client found another engineer who has
taken a simplified approach to the problem that may not be compliant with
either of our views but will get the contractor's three projects permitted
over the counter.

From my perspective, I had to view the practical solution and in the process
understood that there were other potential problems that needed to be
considered. Once I brought up my concerns about the capability of the
existing wood truss roof to carry the additional loads from the panels that
they were not designed for, the client decided their goal was to sell
photovoltaic panels and would therefore find an engineer willing to stick
his neck out and simplify the code back to the 97 UBC four line analysis
type of design.

This does not work for me. I won't put my stamp on anything that I believe
may be a risk unless I consider the alternatives. From what you have
written, the most accurate way to address the problem would essentially work
best if the industry establishes tables of wind values for various
conditions and provide the local engineer with the design loads in order to
allow the engineer only to address the ability of the roof framing
(especially if a metal side plate manufactured wood truss) to support the
reactions at the connections of the panel framework. This puts me in
agreement with your comments about the solar panel manufacturer's
responsibility to address the reserve capacity of the roof (if one exists).

The bottom line is that by the time the project came to me it had been
submitted to the building department and had received a list of corrections.
The client was not willing to take the time for me to come up to speed or to
consider the research that I would have suggested to assure that the roof
could carry the load - especially where the roof is flat and there may be a
ponding problem due to the original design based only on the original
materials used without consideration for what technology may bring in the
future.

Thank you for your response - I do agree with you but when it comes down to
a company with a product looking for a professional willing to stick their
potential liability neck out for a fee - they came to the wrong engineer.

Possibly Bob Garner can carry this further and I certainly would recommend
that you allow him to use your response since it takes the issue back to the
manufacturer's design stage to be more creative when addressing a retrofit
system on a tract style home or one constructed to the IRC prescriptive
standards.

Thanks again,
Dennis

-----Original Message-----
From: Conrad Harrison [mailto:sch.tectonic@bigpond.com]
Sent: Wednesday, August 13, 2008 11:55 PM
To: seaint@seaint.org
Subject: RE: Wind load design for Photovoltaic panel installations

Dennis,

Jordan's approach may be the more difficult to sell to plan checkers, but it
is potentially the more correct approach.

In Wind loading of Structures, by John Holmes, the starting point for the
whole subject is with aerodynamics and fluid flow. He also provides some
guidance for design of roof mounted solar hot water systems, and antennae.

Using AS1170.2 we have drag coefficients for various structural sections,
and also frictional drag requirements over cladding. But still solar panels
and other roof mounted structures are outside the scope of the code: but
then so are most real things.

Using the code some judgement needs to be made regarding the interference of
airflow over the roof and the obstruction of the solar panel. Free monoslope
roofs give some guidance, but gap between panel and roof would have some
form of venturi effect. Then there will be turbulence where the airflow hits
and leaves the solar panel obstructing airflow over the roof surface. The
direction of the wind pressure could be uncertain.

Consider another example, a skillion roof lean-to against the wall to a
higher level gable roof. Does the wall experience wind ward positive
pressure, or more a continuation of the roof suction? What height above the
skillion roof experiences suction, and when does the interference between
the wall and roof cancel out, and the windward wall pressure dominate?

Using the wind loading code is highly dependent on making judgement calls of
worst case conditions for real world buildings which seldom have the shapes
used in the wind tunnel testing.

It is also a matter of how easy it is for you to apply your own design
factor to magnify design loads to allow for uncertainties, and how well the
results are then accepted by those who have to pay for the implementation,
and how practical it is to implement.

It is outside the scope of the code, it can therefore only be a judgement
call: unless some manufacturer willing to do wind tunnel testing, in which
case they will have the test results and no other manufacturer will.

Here we don't have the same liability issues as you have in the US, so here
all parties are generally more willing to take the risk and make and accept
judgements. If risks are explained then losses are also more acceptable.
Insisting on great expense to strengthen something, then experiencing loads
greater than design load and still loosing is good cause for owners to be
unhappy. A balance needs to be made between the expense now, and the cost of
replacement. The hazard to life, is not addressed by the magnitude of the
load, but by the mode of failure and circumstances. When a severe weather
warning is issued then expect hazard to life: not the least of which is
trees being uprooted and crashing through house roofs or bringing cables and
utility poles down. Direct action of wind on the roof is minor hazard to
life: unless in hurricane or tornado territory.

Also it is not the 50 year mean return period wind speed need to worry
about, but the ultimate limit state wind speed with a mean return period of
500 years: and roughly 5% probability of being exceeded for a 25 year life
expectancy for a building: this is the wind which will start to tear the
building apart. Combining this with the 5 percentile resistance, the
probability of the load exceeded and the system below strength is very low:
more likely to be over strength and under loaded if everything worked out
right. None the less failure is inevitable. The question is will it happen
in our life times, will the buildings last long enough that we can move
forward, how often are we hampered from moving forward because of need to
rebuild: both as a society and as an individual?

My point is that generally things are built before regulations are imposed.
Regulations are imposed because of perceived hazard or a few failures, and
initial regulations tend to be prescriptions based on what is known to be
working versus what is known to be failing.

So when there is no existing specific guidance, any rational justification
is better than none. Engineering doesn't make it safe; it simply reduces the
risk of failure compared to having no engineering. With no engineering best
guess of the risk of failure is 50%: either it will or it won't. With
engineering hope to do better than that.

So one option is to start with the resistance of what the installers prefer
to do, then work that back to the maximum pressure coefficient which can be
applied, then compare that against the code. If lucky will get a coefficient
greater than anything in the code.

Using AS1170.2 I can go one step further, and maintain risk at 5% and adjust
life expectancy of the structure, on condition do not drop design wind speed
below 30m/s. (we vary site wind speed with height, then calculate pressure
compare ASCE7 which varies pressure with height)

I think some solar hot water systems only have a life of about 10 years, so
why design the support structure for a longer life, if it needs to be
modified for new systems? And who knows how long a solar cell remains
operational before pollution damages it. Of course the support structure may
be there for as long as the house, with solar panels replaced occasionally.

Further if solar panels are to be mounted on roof tops, then the
manufacturers should consider designing the panels and support structure to
suit the potential reserve capacity in the variety of existing roofs rather
than imposing wide scale assessment of existing dwellings. That is the panel
manufacturers should do the wind loading research and publish the
recommendations for support structure.

Conventional light timber framing represents the minimum resistance
available, if consider that is over stressed in the first instance then,
zero reserve resistance for additional loading. Therefore need an
independent support structure reaching to roof level if that is impractical,
unsightly and unacceptable: then the alternative is to accept lower design
load. A lower design load reduces life expectancy if risk level is
maintained.

And by all accounts from most members of the list conventional timber
framing in the US is considered over stressed when checked against the
structural codes. Therefore if resistance calculated by codes is considered
accurate, then the design load needs to be lower for it to be acceptable,
which once again for a given risk means the life expectancy of conventional
framing is lower than engineered construction. That lower life expectancy is
acceptable to the community and authors of the codes; otherwise conventional
framing would be rejected by the regulators.

All structures designed to a code of practice are at risk of failure, it is
unhelpful to think in terms of providing safety: we are dealing with
uncertainty; there may be no safety at all. Also lawyers don't care what
codes say, but what the designer should have been expected to know.

So sometimes it is necessary to take the difficult path and educate the
building officials, or assist them by getting calculations independently
reviewed before submitting for checking. Another perspective is if the
building officials ask the questions and cause the problems for owners and
builders alike, then they better be capable of understanding the solution.
The person in the building department, who posed the problem, usually can,
and is also likely to accept rational judgement when the codes have no
specific requirements. Also when all the problems and practicalities are
pointed out, building departments are amenable, and introduce some
guidelines for acceptable practice, so as not to cripple local business and
the building products they are supplying.

Whilst most of the work I do comes from manufacturer/builders I don't much
like such businesses which rely on external consultants. I believe they
should employ engineers on staff and properly design and engineer their
products, and otherwise properly assess individual projects and provide
proper documentation for building approval. Rather than wait until the
building officials issue them with 4 pages of questions, then turn up at
some consultant's office crying for help: and a time constraint to avoid
paying the approval fees again. If the product is appropriately designed
then the manufacturer would be one step in front of the regulators.

Given that the owners and contractors will want a 10 minute solution and low
fee, and supplying at maybe a rate of one or more per day.

Really need to assess how quickly can get a conservative answer, and what
risks you are exposed to.

The simple answer is to try pushing some questions back, to both the
manufacturers and the building departments. See what practical compromise
can be reached.

(Oh! the probability stuff is in the commentary to ASCE7, and also the book
by Holmes it is also in AS1170.2 but the probability models are for
Australian conditions.)

Regards
Conrad Harrison
B.Tech (mfg & mech), MIIE, gradTIEAust
mailto:sch.tectonic@bigpond.com
Adelaide
South Australia

******* ****** ******* ******** ******* ******* ******* ***
* Read list FAQ at: http://www.seaint.org/list_FAQ.asp
*
* This email was sent to you via Structural Engineers
* Association of Southern California (SEAOSC) server. To
* subscribe (no fee) or UnSubscribe, please go to:
*
* http://www.seaint.org/sealist1.asp
*
* Questions to seaint-ad@seaint.org. Remember, any email you
* send to the list is public domain and may be re-posted
* without your permission. Make sure you visit our web
* site at: http://www.seaint.org
******* ****** ****** ****** ******* ****** ****** ********

******* ****** ******* ******** ******* ******* ******* ***
* Read list FAQ at: http://www.seaint.org/list_FAQ.asp
*
* This email was sent to you via Structural Engineers
* Association of Southern California (SEAOSC) server. To
* subscribe (no fee) or UnSubscribe, please go to:
*
* http://www.seaint.org/sealist1.asp
*
* Questions to seaint-ad@seaint.org. Remember, any email you
* send to the list is public domain and may be re-posted
* without your permission. Make sure you visit our web
* site at: http://www.seaint.org
******* ****** ****** ****** ******* ****** ****** ********

RE: SDC D Ordinary Moment frame connection using HSS sections

I don’t have the latest version of AWS D1.1, but section 5.10 of the 2004 AWS D1.1 only talks about removal of backing plates for cyclically loaded structures and it states explicitly that backing plates need not be removed for statically loaded structures.  While wind/seismic forces may be cyclic in the truest sense of the word, I’ve always taken the definition of cyclically loaded structures to mean bridges, cranes, machinery supports, etc.  Anyone else have any insight on the definition of a “cyclically loaded structure”?

 

From: Gordon Goodell [mailto:GordonGoodell@harmonydesigninc.com]
Sent: Thursday, August 14, 2008 4:47 PM
To: seaint@seaint.org
Subject: RE: SDC D Ordinary Moment frame connection using HSS sections

 

Mark,

 

AWS D1.1, provision 5.10 requires removal of backing on welds that are transverse to the direction of stress, but not for welds that are parallel.  Maybe at 45º half of the backing should be removed.  Just kidding.  It is a stress concentrator and inhibits ductile behaviour, and you would not want to leave the backing in a SMF, but maybe OK for an OMF with low force levels.  But D1.1 applies to OMF.  SMFs are governed by the seismic supplement, D1.8, which is more restrictive.

 

regards,

Gordon

 

From: Mark D. Baker [mailto:shake4bake@verizon.net]
Sent: Thursday, August 14, 2008 1:40 PM
To: seaint@seaint.org
Subject: RE: SDC D Ordinary Moment frame connection using HSS sections

 

Gordon,

 

Hmmm, in the case of the V, rounding the point of V would aid in reducing stress concentration effects.

 

In the case of tension force at 45 to weld I also am interested in others comments. Could one convince himself that the tension force is resolved as simply as a couple in the plane of top and bottom of beam within column thereby staying out of weld? I guess I’d have to slow down and sketch a stress diagram through the joint to really think this through.

 

To further display my ignorance…..where is it written that backing must be removed when force is at 45 to weld?

 

MDB

 


From: Gordon Goodell [mailto:GordonGoodell@harmonydesigninc.com]
Sent: Thursday, August 14, 2008 11:18 AM
To: seaint@seaint.org
Subject: RE: SDC D Ordinary Moment frame connection using HSS sections

 

Mark,

 

If I’m understanding you correctly, cyclical tension force would be at a 45º angle to the weld, so the backing would have to be removed, which could not be accomplished.  Also, there would be a significant stress increase at the point of the V.

 

This is a really good question.  I’d be interested to know how others deal with it.

 

regards,

Gordon Goodell

 

 

 

Mark D. Baker wrote:

 

“In the situation where column meets beam and the column does not continue past beam, cut ends of column and beam at 45, backing can be installed for this joint.

 

Where column does run past beam, cut notch in column in a V shape (female end) and cut end of beam in a V shape (male end) to insert into the column notch. This joint also will be able to receive backing plates.

 

You are correct that when trying to join the beam to the column face, full pen welds are nearly impossible.”

 

 

 

RE: SDC D Ordinary Moment frame connection using HSS sections

Mark,

 

AWS D1.1, provision 5.10 requires removal of backing on welds that are transverse to the direction of stress, but not for welds that are parallel.  Maybe at 45º half of the backing should be removed.  Just kidding.  It is a stress concentrator and inhibits ductile behaviour, and you would not want to leave the backing in a SMF, but maybe OK for an OMF with low force levels.  But D1.1 applies to OMF.  SMFs are governed by the seismic supplement, D1.8, which is more restrictive.

 

regards,

Gordon

 

From: Mark D. Baker [mailto:shake4bake@verizon.net]
Sent: Thursday, August 14, 2008 1:40 PM
To: seaint@seaint.org
Subject: RE: SDC D Ordinary Moment frame connection using HSS sections

 

Gordon,

 

Hmmm, in the case of the V, rounding the point of V would aid in reducing stress concentration effects.

 

In the case of tension force at 45 to weld I also am interested in others comments. Could one convince himself that the tension force is resolved as simply as a couple in the plane of top and bottom of beam within column thereby staying out of weld? I guess I’d have to slow down and sketch a stress diagram through the joint to really think this through.

 

To further display my ignorance…..where is it written that backing must be removed when force is at 45 to weld?

 

MDB

 


From: Gordon Goodell [mailto:GordonGoodell@harmonydesigninc.com]
Sent: Thursday, August 14, 2008 11:18 AM
To: seaint@seaint.org
Subject: RE: SDC D Ordinary Moment frame connection using HSS sections

 

Mark,

 

If I’m understanding you correctly, cyclical tension force would be at a 45º angle to the weld, so the backing would have to be removed, which could not be accomplished.  Also, there would be a significant stress increase at the point of the V.

 

This is a really good question.  I’d be interested to know how others deal with it.

 

regards,

Gordon Goodell

 

 

 

Mark D. Baker wrote:

 

“In the situation where column meets beam and the column does not continue past beam, cut ends of column and beam at 45, backing can be installed for this joint.

 

Where column does run past beam, cut notch in column in a V shape (female end) and cut end of beam in a V shape (male end) to insert into the column notch. This joint also will be able to receive backing plates.

 

You are correct that when trying to join the beam to the column face, full pen welds are nearly impossible.”

 

 

 

RE: SDC D Ordinary Moment frame connection using HSS sections

Joe,
Regarding OCBF, there are virtually no serious requirements other than the connection strength ( >= 2*design force).
 
If HSS braces are used, I would keep the gusset plates since they allow out of plane buckling of braces which enhances energy dissipation.
 
Suresh Acharya, S.E.


From: Joseph R. Grill [mailto:jrgrill@cableone.net]
Sent: Thursday, August 14, 2008 12:54 PM
To: seaint@seaint.org
Subject: RE: SDC D Ordinary Moment frame connection using HSS sections

Mark and Suresh,

I did see the note in Section 11.1.  It's been a long time since I've done one of these (pre IBC).  In going through the seismic manual I saw the note, but couldn't envision how to make the connection.  Mark, your idea sounds great.  However in reviewing other criteria for the OMF I don't think I can comply with some of those, such as bracing as this is a frame within a stair tower with no floors or perpendicular framing at the horizontal beam locations.

 

The fabricator is open to a concentric braced frame.  I'm looking at single diagonals in the bays (3 bays high x 1bay long).  I think this works.  I do, however have a question regarding this.  I would think that the diagonals could be welded directly at the column beam intersections without gusset plates.  I don't see a requirement for the use of gussets.  Am I correct there.  The loads shouldn't be very high.

 

Thanks for the idea.

Joe

 

From: Mark D. Baker [mailto:shake4bake@verizon.net]
Sent: Thursday, August 14, 2008 9:01 AM
To: seaint@seaint.org
Subject: RE: SDC D Ordinary Moment frame connection using HSS sections

 

Joe,

 

Section 11.1 of the Seismic Provisions for Structural Steel Buildings, AISC 341-05 says:

 

"While these provisions for OMF were primarily developed for use with wide flange shapes, with judgment, they may also be applied to other shapes such as channels, built-up sections, and hollow structural sections (HSS)"

 

In the situation where column meets beam and the column does not continue past beam, cut ends of column and beam at 45, backing can be installed for this joint.

 

Where column does run past beam, cut notch in column in a V shape (female end) and cut end of beam in a V shape (male end) to insert into the column notch. This joint also will be able to receive backing plates.

 

You are correct that when trying to join the beam to the column face, full pen welds are nearly impossible.

 

Regards,

 

Mark D. Baker

Baker Engineering

 


From: Joseph R. Grill [mailto:jrgrill@cableone.net]
Sent: Wednesday, August 13, 2008 9:28 PM
To: seaint@seaint.org
Subject: SDC D Ordinary Moment frame connection using HSS sections

 

Can HSS sections be used in an Ordinary Moment Frame in a SDC D.  I can't see, in the seismic design manual,  where it is specifically excluded, but I can't find any information for the HSS Beam to HSS column connection design.  It seems that it can't be done since a full pen weld is difficult if not impossible to do for a HSS beam to HSS Column face.  If there is an example out there I would love to see it.  I am doing some work for a fabricator and they are expecting HSS sections due to what is seen in the construction documents.  I have to let him know real soon if he will need to go to wide flange members.

 

Thanks for the help,

Joe Grill

 

Joseph R. Grill, PE

Verde Valley Engineering, PLLC

2220 Sky Drive

Clarkdale, AZ 86324

Ph. (928) 600-5459

Fax (928) 649-3659

email: VVEng@cableone.net