Friday, April 10, 2009

RE: Retaining wall footing resultant CBC

I like your idea.

 

Gautam

 


From: Garner, Robert [mailto:rgarner@moffattnichol.com]
Sent: Friday, April 10, 2009 10:37 AM
To: seaint@seaint.org; mhemstad@mbjeng.com
Subject: RE: Retaining wall footing resultant CBC

 

Before negotiation meetings with new clients, we always put up posters in the conference room of various structural failures.  Then when the client asks us why this or why that, we need only lean back in our chairs, look at one of the posters, and ask our business manager out loud, "Does our insurance cover that?" 

 


From: Rhkratzse@aol.com [mailto:Rhkratzse@aol.com]
Sent: Friday, April 10, 2009 9:49 AM
To: mhemstad@mbjeng.com; seaint@seaint.org
Subject: Re: Retaining wall footing resultant CBC

 

In a message dated 4/10/09 7:37:42 AM, mhemstad@mbjeng.com writes:

It takes what it takes.  It costs what it costs.  There are things we can cut, and things we can't. 
Geez I sound old.


Love it, Mike!  What a great philosophy (except the last phrase, of course).

Ralph Hueston Kratz, S.E.
Richmond CA USA



**************
Worried about job security? Check out the 5 safest jobs in a recession. (http://jobs.aol.com/gallery/growing-job-industries?ncid=emlcntuscare00000003)

RE: Beam-column joint details

Bill,

All the outside column bars need to be developed is a distance represented by the beam depth( less cover),
and that can be accomplished by standard hooks or headed bars, if there is not enough depth available then
you will need smaller diameter bars, additional transverse reinforcement, and
or a deeper beam.This is the same as the beam bars being developed in the column say in a
middle floor, just rotate the joint 90 degrees

Happy Friday

Tarek Mokhtar, SE
Laguna Beach






Since I didn't get any responses, I'll expand on my thoughts: Where negative moments occur at a wall corner, the outside horizontal bars are typically spliced for moment continuity. Similarly, where a fixed base exterior wall is externally loaded, the outside vertical wall bars should be spliced to the bottom slab bars for outside moment continuity (if no footing extension). The same concept should apply to moment continuity at a roof beam connection to an exterior column, but I often don't see such rebar details addressed in such applications.
 
ACI 352R-02, "Recommendations for Design of Beam-Column Connections in Monolithic Reinforced Concrete Structures" should be the best reference to address this condition - but it does not address it as well as I would like.  It actually contradicts my approach to some extent as it only addresses beam bars with standard hooks or with headed bars into the top of column (lacking bar continuity around the corner) - and then it shows a tremendous amount of transverse reinforcement in the joint and discusses its use for ductile seismic applications.  It does not appear to address simpler spliced longitudinal bar details without a mass of transverse reinforcement for low-seismic applications.
 
I've questioned a design I was asked to review but the originator doesn't want to change their details.  I'm searching for references that help justify what detailing should be used, but I'm finding very little in available literature for this particular case.
 
Bill Sherman
CH2M HILL / DEN
720-286-2792
 


From: William.Sherman@CH2M.com [mailto:William.Sherman@CH2M.com]
Sent: Thursday, April 09, 2009 1:15 PM
To: seaint@seaint.org
Subject: Beam-column joint details

Question: How do you detail longitudinal beam and column rebar at a monolithic beam-column joint, at than exterior column at roof level?
 
Addl info for current consideration:  Low-seismic region; two-story structure; rigid concrete frame resists lateral loads; concrete roof beam frames into top of exterior concrete column; typical beam details show top and bottom bars with standard hooks extended into columns; and standard hooks are shown at tops of longitudinal column bars.
 
Most references show a detail at an intermediate floor level where the column is continuous above - standard hooks at top and bottom beam bars are reasonable for that configuration.  But at the top of column, hooks at beam bars and at column bars do not appear to provide sufficient continuity for moment transfer around the outside face of the beam and column.  Nevertheless, drawings frequently show "typical beam details" for these columns as well - and the design engineers argue that this meets the code. 
 
Any thoughts?  Any references to justify your approach?
 
Bill
William Sherman - CH2M HILL / Denver
Principal Structural Technologist - Water Business Group
william.sherman@ch2m.com
720.286.2792
 


--  
Tarek Mokhtar, SE
TMM Structural Engineers, Inc
31645 S. Coast Hwy
Laguna Beach, CA., 92651
949-499-6254
949-499-2777 Fax




RE: Beam-column joint details

Since I didn't get any responses, I'll expand on my thoughts: Where negative moments occur at a wall corner, the outside horizontal bars are typically spliced for moment continuity. Similarly, where a fixed base exterior wall is externally loaded, the outside vertical wall bars should be spliced to the bottom slab bars for outside moment continuity (if no footing extension). The same concept should apply to moment continuity at a roof beam connection to an exterior column, but I often don't see such rebar details addressed in such applications.
 
ACI 352R-02, "Recommendations for Design of Beam-Column Connections in Monolithic Reinforced Concrete Structures" should be the best reference to address this condition - but it does not address it as well as I would like.  It actually contradicts my approach to some extent as it only addresses beam bars with standard hooks or with headed bars into the top of column (lacking bar continuity around the corner) - and then it shows a tremendous amount of transverse reinforcement in the joint and discusses its use for ductile seismic applications.  It does not appear to address simpler spliced longitudinal bar details without a mass of transverse reinforcement for low-seismic applications.
 
I've questioned a design I was asked to review but the originator doesn't want to change their details.  I'm searching for references that help justify what detailing should be used, but I'm finding very little in available literature for this particular case.
 
Bill Sherman
CH2M HILL / DEN
720-286-2792
 


From: William.Sherman@CH2M.com [mailto:William.Sherman@CH2M.com]
Sent: Thursday, April 09, 2009 1:15 PM
To: seaint@seaint.org
Subject: Beam-column joint details

Question: How do you detail longitudinal beam and column rebar at a monolithic beam-column joint, at than exterior column at roof level?
 
Addl info for current consideration:  Low-seismic region; two-story structure; rigid concrete frame resists lateral loads; concrete roof beam frames into top of exterior concrete column; typical beam details show top and bottom bars with standard hooks extended into columns; and standard hooks are shown at tops of longitudinal column bars.
 
Most references show a detail at an intermediate floor level where the column is continuous above - standard hooks at top and bottom beam bars are reasonable for that configuration.  But at the top of column, hooks at beam bars and at column bars do not appear to provide sufficient continuity for moment transfer around the outside face of the beam and column.  Nevertheless, drawings frequently show "typical beam details" for these columns as well - and the design engineers argue that this meets the code. 
 
Any thoughts?  Any references to justify your approach?
 
Bill
William Sherman - CH2M HILL / Denver
Principal Structural Technologist - Water Business Group
720.286.2792
 

RE: Retaining wall footing resultant CBC

USACE allows the resultant to be outside the middle third for Unusual Loads or Earthquake Loads on retaining walls (Table 4-1, EM 1110-2-2502).  I agree that I would maintain the resultant in the middle third for sustained loads or more critical load cases.  I've allowed the resultant outside the middle third for design wind load on a masonry fence - and I told the owner that the wall might deflect (rotate) more under wind load using this design, but it saves on footing width.
 
I also believe that USACE allows resisting soil pressure to be up to one-half the theoretical passive pressure if small movement is allowed, since the deformation to develop one-half of passive pressure is much smaller than that to develop full passive pressure.
 
Although designing for active pressure on the resisting side is not logical based on expected wall movement, I thought I once saw a reference that suggested using it for evaluation of wall stresses as a  "conservative" assumption for minimum soil pressure - but most engineers just neglect resisting soil pressure for wall design.
 
Bill Sherman
CH2M HILL / DEN
720-286-2792
 


From: Michael Hemstad [mailto:mhemstad@mbjeng.com]
Sent: Friday, April 10, 2009 8:34 AM
To: seaint@seaint.org
Subject: Retaining wall footing resultant CBC

I agree with Steve.  When I design retaining walls, I put At-rest pressure on the back face.  Remember that the wall has to move slightly to engage the soil skeleton enough to apply only Active-level forces.  In my mind, the next time it rains, the soil settles and applies at-rest level force.  Then, if the wall can move again, the soil skeleton is re-mobilized and we're back to active pressure.
 
The wall can't keep moving, or at least I don't want it to.  Around here we've got a lot of short modular block walls with negative batter.  They weren't built that way, but that's how they are now.  After 15 or 20 years they get taken down and rebuilt by the same landscape companies that screwed them up the first time.
 
I also design my footings for resultant in the middle third.  The prospect of permanent uplift force (negative pressure) on the heel does not appeal to me.  Again, with ground water, frost, construction compaction, and whatever else can happen, any potential gap under the heel will eventually fill in.  Then you don't have the downward force on the heel that you were counting on (because it can bear now) and your wall has to tip forward to re-mobilize heel uplift.  Same problem, different direction, same result.
 
As far as the front face fill goes, I will use it in an At-rest state to resist sliding.  My understanding (from Bowles) is that the movement to mobilize passive resistance is something like an order of magnitude greater than the movement necessary to mobilize active force.  In other words, you don't want the wall to move enough to engage passive pressure.  You don't want the wall to move at all.  So design for at-rest force all around.
 
Comments about footings getting big (and walls getting thick and geez that's a lot of reinforcing) I try to ignore.  I have designed flood walls for the Army Corps of Engineers, where the footing length is around 1.4 times the wall height.  That looks excessive until you look at the force of saturated fill, the strength of saturated foundation material, the effects of moving water on your subgrade, the potential for some Emergency Management bureaucrat to give in to inevitable pressure to install flashboards when the flood exceeds the design level (it will), and the value of what the wall is protecting--in my case, on one project, half of downtown St. Paul.
 
It takes what it takes.  It costs what it costs.  There are things we can cut, and things we can't.  Weigh the marginal cost of the bigger footing against the cost of failure.
 
Geez I sound old.
 
Mike Hemstad, P.E., S.E.
MBJ
Minneapolis, Minnesota
 
 
Steve Gordin wrote:
 
As far as I know, active pressure on a cantilevered retaining wall =
develops following some movement (rotation) of that wall under the =
pressure from the retained soil. If we have active pressure on the =
retained side, we cannot physically have a simultaneous active pressure =
on the toe side, where the movement of the wall occurs toward the soil, =
i.e., in the opposite direction. =20
The program essentially combines the active and passive pressures on the =
toe side to resist the active pressure on the heel side. This does not =
appear physically obvious within the theories/assumptions used.=20
Can you please comment on the physical nature behind that option?
Thank you,
V. Steve Gordin, SE
Irvine CA

Re: Retaining wall footing resultant CBC

Old?  Maybe; but live.
 
Regards,
 
H. Daryl Richardson
----- Original Message -----
Sent: Friday, April 10, 2009 10:48 AM
Subject: Re: Retaining wall footing resultant CBC

In a message dated 4/10/09 7:37:42 AM, mhemstad@mbjeng.com writes:
It takes what it takes.  It costs what it costs.  There are things we can cut, and things we can't. 
Geez I sound old.

Love it, Mike!  What a great philosophy (except the last phrase, of course).

Ralph Hueston Kratz, S.E.
Richmond CA USA



**************
Worried about job security? Check out the 5 safest jobs in a recession. (http://jobs.aol.com/gallery/growing-job-industries?ncid=emlcntuscare00000003)

RE: Retaining wall footing resultant CBC

I hope not - EFP should be what is appropriate for driving soil pressure based on the structure's ability to move. I often use at-rest pressure, such as for rigid box structures, walls supported at the top, or liquid-containing structures where walls are typically more rigid.
 
Bill Sherman
CH2M HILL / DEN
720-286-2792
 


From: Michel Blangy [mailto:mblangy@satco-inc.com]
Sent: Friday, April 10, 2009 11:48 AM
To: seaint@seaint.org
Subject: RE: Retaining wall footing resultant CBC

Can someone cite a reference establishing EFP as soil density * Ka (active) and NOT soil density * ko (at-rest)?
 
Thanks,
 
Michel
-----Original Message-----
From: Michael Hemstad [mailto:mhemstad@mbjeng.com]
Sent: Friday, April 10, 2009 7:34 AM
To: seaint@seaint.org
Subject: Retaining wall footing resultant CBC

I agree with Steve.  When I design retaining walls, I put At-rest pressure on the back face.  Remember that the wall has to move slightly to engage the soil skeleton enough to apply only Active-level forces.  In my mind, the next time it rains, the soil settles and applies at-rest level force.  Then, if the wall can move again, the soil skeleton is re-mobilized and we're back to active pressure.

RE:

In the Sanskrit tradition, this sound is called "Anahata Nada," the "Unstruck Sound." Literally, this means "the sound that is not made by two things striking together." The point of this particular distinction is that all ordinary audible sounds are made by at least two elements: bow and string; drum and stick; two vocal cords; two lips against the mouthpiece of the trumpet; the double reed of the oboe; waves against the shore; wind against the leaves. All sounds within our range of hearing are created by things visible or invisible, striking each other or vibrating together, creating pulsing waves of air molecules which our ears and brain interpret as sound.

So, sound that is not made of two things striking together is the sound of primal energy, the sound of the universe itself. Joseph Campbell likens this unstruck vibration to the humming of an electrical transformer, or the (to our ears) unheard hummings of atoms and molecules.

And the ancients say that the audible sound which most resembles this unstruck sound is the syllable OM. Tradition has it that this ancient mantra is composed of four elements: the first three are vocal sounds: A, U, and M. The fourth sound, unheard, is the silence which begins and ends the audible sound, the silence which surrounds it.

"A" (pronounced "AH" as in "father") resonates in the center of the mouth. It represents normal waking consciousness, in which subject and object exist as separate entities. This is the level of mechanics, science, logical reason, the lower three chakras. Matter exists on a gross level, is stable and slow to change.

"U" (pronounced as in "who") transfers the sense of vibration to the back of the mouth, and shifts the allegory to the level of dream consciousness. Here, object and subject become intertwined in awareness. Both are contained within us. Matter becomes subtle, more fluid, rapidly changing. This is the realm of dreams, divinities, imagination, the inner world.

"M" is the third element, humming with lips gently closed. This sound resonates forward in the mouth and buzzes throughout the head. (Try it.) This sound represents the realm of deep, dreamless sleep. There is neither observing subject nor observed object. All are one, and nothing. Only pure consciousness exists, unseen, pristine, latent, covered with darkness. This is the cosmic night, the interval between cycles of creation, the womb of the divine Mother.

 

-----Original Message-----
From: Dilip Patel [mailto:dp_enco@yahoo.com]
Sent: Friday, April 10, 2009 10:55 AM
To: seaint@seaint.org
Subject: Re:

you mean: OHmmmmmmmmmmmmmmm


From: Michel Blangy <mblangy@satco-inc.com>
To: seaint@seaint.org
Sent: Friday, April 10, 2009 1:54:00 PM
Subject: RE:

AUMmmmmmmmmmmmmm
-----Original Message-----
From: Dilip Patel [mailto:dp_enco@yahoo.com]
Sent: Friday, April 10, 2009 10:43 AM
To: William.Sherman@CH2M.com; seaint@seaint.org
Subject:

Thanks for clarification.

DP


Re:

you mean: OHmmmmmmmmmmmmmmm


From: Michel Blangy <mblangy@satco-inc.com>
To: seaint@seaint.org
Sent: Friday, April 10, 2009 1:54:00 PM
Subject: RE:

AUMmmmmmmmmmmmmm
-----Original Message-----
From: Dilip Patel [mailto:dp_enco@yahoo.com]
Sent: Friday, April 10, 2009 10:43 AM
To: William.Sherman@CH2M.com; seaint@seaint.org
Subject:

Thanks for clarification.

DP


RE:

AUMmmmmmmmmmmmmm
-----Original Message-----
From: Dilip Patel [mailto:dp_enco@yahoo.com]
Sent: Friday, April 10, 2009 10:43 AM
To: William.Sherman@CH2M.com; seaint@seaint.org
Subject:

Thanks for clarification.

DP

RE: Retaining wall footing resultant CBC

Can someone cite a reference establishing EFP as soil density * Ka (active) and NOT soil density * ko (at-rest)?
 
Thanks,
 
Michel
-----Original Message-----
From: Michael Hemstad [mailto:mhemstad@mbjeng.com]
Sent: Friday, April 10, 2009 7:34 AM
To: seaint@seaint.org
Subject: Retaining wall footing resultant CBC

I agree with Steve.  When I design retaining walls, I put At-rest pressure on the back face.  Remember that the wall has to move slightly to engage the soil skeleton enough to apply only Active-level forces.  In my mind, the next time it rains, the soil settles and applies at-rest level force.  Then, if the wall can move again, the soil skeleton is re-mobilized and we're back to active pressure.
Thanks for clarification.

DP

RE: Retaining wall footing resultant CBC

Before negotiation meetings with new clients, we always put up posters in the conference room of various structural failures.  Then when the client asks us why this or why that, we need only lean back in our chairs, look at one of the posters, and ask our business manager out loud, "Does our insurance cover that?" 

 


From: Rhkratzse@aol.com [mailto:Rhkratzse@aol.com]
Sent: Friday, April 10, 2009 9:49 AM
To: mhemstad@mbjeng.com; seaint@seaint.org
Subject: Re: Retaining wall footing resultant CBC

 

In a message dated 4/10/09 7:37:42 AM, mhemstad@mbjeng.com writes:

It takes what it takes.  It costs what it costs.  There are things we can cut, and things we can't. 
Geez I sound old.


Love it, Mike!  What a great philosophy (except the last phrase, of course).

Ralph Hueston Kratz, S.E.
Richmond CA USA



**************
Worried about job security? Check out the 5 safest jobs in a recession. (http://jobs.aol.com/gallery/growing-job-industries?ncid=emlcntuscare00000003)

Re: Italy quake: L'Aquila's new public hospital

Paul.

Evacuate, no problem. But the hospital staff should be able to go back in real quick and get to work on helping people. Doesn't sound like this was the case.

-gm

On Thu, Apr 9, 2009 at 9:08 PM, Paul Ransom <ad026@hwcn.org> wrote:
Gerard,
With respect, I have heard no comparison of design vs event.

Current US standard practice may not be reflective of design/construction
requirements in Italy at that time. It was not long ago that seismic design
philosophy on this side of the pond underwent a radical shift, essentially,
saying that everything done before is not as good as it could be. It took
even longer for California to legally respond to that state-of-the-art
knowledge. As I understand it, there is a substantial inventory of buildings
waiting for retrofit work.

Perhaps the hospital was evacuated due to concerns based on cosmetic damage
... and exacerbated by the appraisal of an available architect.

Regards
Paul


> Subject: Re: Italy quake: L'Aquila's new public hospital
> From: "Gerard Madden, SE" <gmse4603@gmail.com>
> To: seaint@seaint.org
>
> --0016363109bb9844300467136a83
> Content-Type: text/plain; charset=ISO-8859-1
> Content-Transfer-Encoding: 7bit
>
> I agree with Paul on 1 and 2, but not on 3
>
> As is standard practice here in California, hospitals (with patients, not
> office or admin buildings) should remain available for immediate occupancy
> after major seismic event, not simply collapse prevention. If this hospital
> is really only 9 years old, then something's wrong (code, engineer,
> architect, inspection/ code enforcement, or construction quality or some
> combination of them all),
>
> -gm


******* ****** ******* ******** ******* ******* ******* ***
*   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
*
*   This email was sent to you via Structural Engineers
*   Association of Southern California (SEAOSC) server. To
*   subscribe (no fee) or UnSubscribe, please go to:
*
*   http://www.seaint.org/sealist1.asp
*
*   Questions to seaint-ad@seaint.org. Remember, any email you
*   send to the list is public domain and may be re-posted
*   without your permission. Make sure you visit our web
*   site at: http://www.seaint.org
******* ****** ****** ****** ******* ****** ****** ********

Re: Italy quake: L'Aquila's new public hospital

On Thu, Apr 9, 2009 at 9:08 PM, Paul Ransom <ad026@hwcn.org> wrote:

Perhaps the hospital was evacuated due to concerns based on cosmetic damage
... and exacerbated by the appraisal of an available architect.
......................

ROME (Reuters) - L'Aquila's new public hospital was hailed as a state-of-the-art, earthquake-proof building when it opened in 2000. But it collapsed along with many centuries-old monuments in the earthquake that struck the city on Monday.

The San Salvatore hospital, evacuated after its walls gave way, forcing doctors to treat quake victims and ordinary patients in a courtyard, has exposed inadequate infrastructure in the area. 
........................

If walls are giving way, it doesn't necessarily sound like cosmetic damage...  Maybe the Reuters reporter was a native Italian-as-first-language, and it doesn't quite translate correctly in English (UK/US/CAN)...  And, maybe the walls that gave way were non-structural partitions.  

Regardless, it's ludicrous that such damage could occur to a new "state-of-the-art" facility.  To have such a "it's not in our culture" attitude with a shrug of the shoulders is shameful.  I'll zip it now...

--
David Topete, SE

Re: Retaining wall footing resultant CBC

In a message dated 4/10/09 7:37:42 AM, mhemstad@mbjeng.com writes:
It takes what it takes.  It costs what it costs.  There are things we can cut, and things we can't. 
Geez I sound old.

Love it, Mike!  What a great philosophy (except the last phrase, of course).

Ralph Hueston Kratz, S.E.
Richmond CA USA



**************
Worried about job security? Check out the 5 safest jobs in a recession. (http://jobs.aol.com/gallery/growing-job-industries?ncid=emlcntuscare00000003)

Re: Hollow Core Topping and Conduit

They are just single spanning planks at this location (multi-story jail cell area with cmu) so there is no abutting ends. Now they are saying up to 3/4" diameter conduit.
 
Now I am thinking that running the conduit in the topping is alright (perpendicular to the HC spans), because the topping should be bonded well enough to transfer the shear.  In other words, the load path is shear in the topping, then to the hollow core itself through topping bond where the topping is being interrupted by conduit.
 
 
WH 

On Fri, Apr 10, 2009 at 10:40 AM, Paul Blomberg <paul.blomberg@gmail.com> wrote:
I've never actually seen 3/8" conduit (EMT) actually used.  Smallest is normally 1/2".  Could the conduit fit at the ends of the HC planks where they butt together, below the 2" topping slab?
 
Paul.

 
On 4/9/09, Harold Sprague <spraguehope@hotmail.com> wrote:
Talk to the HC mfgr.  They can drill and place the conduit in the planks at mid height before it leaves the plant. 

Regards, Harold Sprague


 

Date: Thu, 9 Apr 2009 19:01:02 -0400
Subject: Hollow Core Topping and Conduit
From: gtg740p@gmail.com
To: seaint@seaint.org

I have some 3/8" diameter conduit that needs to be run perpendicular to the hollow core slab units (perpendicular to the cores) for the entire width of the building. The conduit cannot go below the HC and the HC is 6" thick with 2" of topping. I don't want to mess up the HC diaphragm topping slab but I don't see any other way to run this conduit and it cannot be placed above the topping slab either. Any ideas on how I can still get the diaphragm shear transfer if the conduit is embedded in the 2" topping slab? I am using a heavy welded wire mesh in the topping slab for the rest of the diaphragm. 
 
Will H


Rediscover Hotmail®: Get quick friend updates right in your inbox. Check it out.


Re: Hollow Core Topping and Conduit

I've never actually seen 3/8" conduit (EMT) actually used.  Smallest is normally 1/2".  Could the conduit fit at the ends of the HC planks where they butt together, below the 2" topping slab?
 
Paul.

 
On 4/9/09, Harold Sprague <spraguehope@hotmail.com> wrote:
Talk to the HC mfgr.  They can drill and place the conduit in the planks at mid height before it leaves the plant. 

Regards, Harold Sprague


 

Date: Thu, 9 Apr 2009 19:01:02 -0400
Subject: Hollow Core Topping and Conduit
From: gtg740p@gmail.com
To: seaint@seaint.org

I have some 3/8" diameter conduit that needs to be run perpendicular to the hollow core slab units (perpendicular to the cores) for the entire width of the building. The conduit cannot go below the HC and the HC is 6" thick with 2" of topping. I don't want to mess up the HC diaphragm topping slab but I don't see any other way to run this conduit and it cannot be placed above the topping slab either. Any ideas on how I can still get the diaphragm shear transfer if the conduit is embedded in the 2" topping slab? I am using a heavy welded wire mesh in the topping slab for the rest of the diaphragm. 
 
Will H


Rediscover Hotmail®: Get quick friend updates right in your inbox. Check it out.

Retaining wall footing resultant CBC

I agree with Steve.  When I design retaining walls, I put At-rest pressure on the back face.  Remember that the wall has to move slightly to engage the soil skeleton enough to apply only Active-level forces.  In my mind, the next time it rains, the soil settles and applies at-rest level force.  Then, if the wall can move again, the soil skeleton is re-mobilized and we're back to active pressure.
 
The wall can't keep moving, or at least I don't want it to.  Around here we've got a lot of short modular block walls with negative batter.  They weren't built that way, but that's how they are now.  After 15 or 20 years they get taken down and rebuilt by the same landscape companies that screwed them up the first time.
 
I also design my footings for resultant in the middle third.  The prospect of permanent uplift force (negative pressure) on the heel does not appeal to me.  Again, with ground water, frost, construction compaction, and whatever else can happen, any potential gap under the heel will eventually fill in.  Then you don't have the downward force on the heel that you were counting on (because it can bear now) and your wall has to tip forward to re-mobilize heel uplift.  Same problem, different direction, same result.
 
As far as the front face fill goes, I will use it in an At-rest state to resist sliding.  My understanding (from Bowles) is that the movement to mobilize passive resistance is something like an order of magnitude greater than the movement necessary to mobilize active force.  In other words, you don't want the wall to move enough to engage passive pressure.  You don't want the wall to move at all.  So design for at-rest force all around.
 
Comments about footings getting big (and walls getting thick and geez that's a lot of reinforcing) I try to ignore.  I have designed flood walls for the Army Corps of Engineers, where the footing length is around 1.4 times the wall height.  That looks excessive until you look at the force of saturated fill, the strength of saturated foundation material, the effects of moving water on your subgrade, the potential for some Emergency Management bureaucrat to give in to inevitable pressure to install flashboards when the flood exceeds the design level (it will), and the value of what the wall is protecting--in my case, on one project, half of downtown St. Paul.
 
It takes what it takes.  It costs what it costs.  There are things we can cut, and things we can't.  Weigh the marginal cost of the bigger footing against the cost of failure.
 
Geez I sound old.
 
Mike Hemstad, P.E., S.E.
MBJ
Minneapolis, Minnesota
 
 
Steve Gordin wrote:
 
As far as I know, active pressure on a cantilevered retaining wall =
develops following some movement (rotation) of that wall under the =
pressure from the retained soil. If we have active pressure on the =
retained side, we cannot physically have a simultaneous active pressure =
on the toe side, where the movement of the wall occurs toward the soil, =
i.e., in the opposite direction. =20
The program essentially combines the active and passive pressures on the =
toe side to resist the active pressure on the heel side. This does not =
appear physically obvious within the theories/assumptions used.=20
Can you please comment on the physical nature behind that option?
Thank you,
V. Steve Gordin, SE
Irvine CA

Thursday, April 9, 2009

Re: Italy quake: L'Aquila's new public hospital

Gerard,
With respect, I have heard no comparison of design vs event.

Current US standard practice may not be reflective of design/construction
requirements in Italy at that time. It was not long ago that seismic design
philosophy on this side of the pond underwent a radical shift, essentially,
saying that everything done before is not as good as it could be. It took
even longer for California to legally respond to that state-of-the-art
knowledge. As I understand it, there is a substantial inventory of buildings
waiting for retrofit work.

Perhaps the hospital was evacuated due to concerns based on cosmetic damage
... and exacerbated by the appraisal of an available architect.

Regards
Paul


> Subject: Re: Italy quake: L'Aquila's new public hospital
> From: "Gerard Madden, SE" <gmse4603@gmail.com>
> To: seaint@seaint.org
>
> --0016363109bb9844300467136a83
> Content-Type: text/plain; charset=ISO-8859-1
> Content-Transfer-Encoding: 7bit
>
> I agree with Paul on 1 and 2, but not on 3
>
> As is standard practice here in California, hospitals (with patients, not
> office or admin buildings) should remain available for immediate occupancy
> after major seismic event, not simply collapse prevention. If this hospital
> is really only 9 years old, then something's wrong (code, engineer,
> architect, inspection/ code enforcement, or construction quality or some
> combination of them all),
>
> -gm


******* ****** ******* ******** ******* ******* ******* ***
* Read list FAQ at: http://www.seaint.org/list_FAQ.asp
*
* This email was sent to you via Structural Engineers
* Association of Southern California (SEAOSC) server. To
* subscribe (no fee) or UnSubscribe, please go to:
*
* http://www.seaint.org/sealist1.asp
*
* Questions to seaint-ad@seaint.org. Remember, any email you
* send to the list is public domain and may be re-posted
* without your permission. Make sure you visit our web
* site at: http://www.seaint.org
******* ****** ****** ****** ******* ****** ****** ********

RE: Welding Procedure

I could not find anything underlined to indicate a change in the fillet welding procedure. 
Regards, Harold Sprague


 

From: ASLCSE@aol.com
Date: Thu, 9 Apr 2009 20:37:20 -0400
Subject: Welding Procedure
To: seaint@seaint.org

Hello Engineering Friends,
 
Is there a difference in the 2000 and 2006 AWS D1.1 welding procedure for fillet welds?
(I do not have the 2006 AWS D1.1)
 
Thanks for your upcoming comments.
 
Antonio S. "Tony" Luisoni, SE


New Deals on Dell Netbooks - Now starting at $299


Rediscover Hotmail®: Now available on your iPhone or BlackBerry Check it out.

RE: Hollow Core Topping and Conduit

Talk to the HC mfgr.  They can drill and place the conduit in the planks at mid height before it leaves the plant. 

Regards, Harold Sprague


 

Date: Thu, 9 Apr 2009 19:01:02 -0400
Subject: Hollow Core Topping and Conduit
From: gtg740p@gmail.com
To: seaint@seaint.org

I have some 3/8" diameter conduit that needs to be run perpendicular to the hollow core slab units (perpendicular to the cores) for the entire width of the building. The conduit cannot go below the HC and the HC is 6" thick with 2" of topping. I don't want to mess up the HC diaphragm topping slab but I don't see any other way to run this conduit and it cannot be placed above the topping slab either. Any ideas on how I can still get the diaphragm shear transfer if the conduit is embedded in the 2" topping slab? I am using a heavy welded wire mesh in the topping slab for the rest of the diaphragm. 
 
Will H


Rediscover Hotmail®: Get quick friend updates right in your inbox. Check it out.

Welding Procedure

Hello Engineering Friends,
 
Is there a difference in the 2000 and 2006 AWS D1.1 welding procedure for fillet welds?
(I do not have the 2006 AWS D1.1)
 
Thanks for your upcoming comments.
 
Antonio S. "Tony" Luisoni, SE


New Deals on Dell Netbooks - Now starting at $299

Hollow Core Topping and Conduit

I have some 3/8" diameter conduit that needs to be run perpendicular to the hollow core slab units (perpendicular to the cores) for the entire width of the building. The conduit cannot go below the HC and the HC is 6" thick with 2" of topping. I don't want to mess up the HC diaphragm topping slab but I don't see any other way to run this conduit and it cannot be placed above the topping slab either. Any ideas on how I can still get the diaphragm shear transfer if the conduit is embedded in the 2" topping slab? I am using a heavy welded wire mesh in the topping slab for the rest of the diaphragm. 
 
Will H

Re: Retaining wall footing resultant CBC

Dear Mr. Brooks,
 
As far as I know, active pressure on a cantilevered retaining wall develops following some movement (rotation) of that wall under the pressure from the retained soil.  If we have active pressure on the retained side, we cannot physically have a simultaneous active pressure on the toe side, where the movement of the wall occurs toward the soil, i.e., in the opposite direction. 
 
The program essentially combines the active and passive pressures on the toe side to resist the active pressure on the heel side.  This does not appear physically obvious within the theories/assumptions used. 
 
Can you please comment on the physical nature behind that option?
 
Thank you,
 
V. Steve Gordin, SE
Irvine CA    
 
 
----- Original Message -----
Sent: Thursday, April 09, 2009 14:48
Subject: RE: Retaining wall footing resultant CBC

Steve   

Although a foot or two of soil over the toe would not be significant, Retain Pro allows the option since a greater height over the toe could significantly reduce overturning and sliding due to its countering effect.  It's the designer's option.  See page 42 of the RP user's manual.

Hugh Brooks, SE

 

From: SGE Structural [mailto:sgordin@sgeconsulting.com]
Sent: Thursday, April 09, 2009 10:22 AM
To: seaint@seaint.org
Subject: Re: Retaining wall footing resultant CBC

 

Dear Mr. Brooks,

 

Could you please comment on the rationale behind the available input of "active soil pressure on the toe side"? 

 

I cannot come up with any physical justification for the use of that option. To the best of my knowledge, the RetainPro and Enercalc manuals are silent on the issue.  

 

Thanks,

 

V. Steve Gordin, SE
Irvine CA
 

 

----- Original Message -----

From: Hugh Brooks

Sent: Thursday, April 09, 2009 09:49

Subject: RE: Retaining wall footing resultant CBC

 

This is an arguable issue, but I accept the design if outside middle third if soil pressure OK and stability >1,5.

Hugh

 

From: Jeff Smith [mailto:jeffsmith7@comcast.net]
Sent: Thursday, April 09, 2009 9:44 AM
To: seaint@seaint.org
Subject: Retaining wall footing resultant CBC

 

California Building Code section 1806A.1 requires the resultant must be in the middle half using 1605A.3 load combinations. I don't see this requirement in chapter 1806. For non essential facilities are there any requirements for the retaining wall resultant, or do we just need a 1.5 safety factor?

 

Jeff

RE: Retaining wall footing resultant CBC

Steve   

Although a foot or two of soil over the toe would not be significant, Retain Pro allows the option since a greater height over the toe could significantly reduce overturning and sliding due to its countering effect.  It’s the designer’s option.  See page 42 of the RP user’s manual.

Hugh Brooks, SE

 

From: SGE Structural [mailto:sgordin@sgeconsulting.com]
Sent: Thursday, April 09, 2009 10:22 AM
To: seaint@seaint.org
Subject: Re: Retaining wall footing resultant CBC

 

Dear Mr. Brooks,

 

Could you please comment on the rationale behind the available input of "active soil pressure on the toe side"? 

 

I cannot come up with any physical justification for the use of that option. To the best of my knowledge, the RetainPro and Enercalc manuals are silent on the issue.  

 

Thanks,

 

V. Steve Gordin, SE
Irvine CA
 

 

----- Original Message -----

From: Hugh Brooks

Sent: Thursday, April 09, 2009 09:49

Subject: RE: Retaining wall footing resultant CBC

 

This is an arguable issue, but I accept the design if outside middle third if soil pressure OK and stability >1,5.

Hugh

 

From: Jeff Smith [mailto:jeffsmith7@comcast.net]
Sent: Thursday, April 09, 2009 9:44 AM
To: seaint@seaint.org
Subject: Retaining wall footing resultant CBC

 

California Building Code section 1806A.1 requires the resultant must be in the middle half using 1605A.3 load combinations. I don't see this requirement in chapter 1806. For non essential facilities are there any requirements for the retaining wall resultant, or do we just need a 1.5 safety factor?

 

Jeff

RE: Cassion Steel Casing check

You are correct, that is at-rest pressure.

 

Bob

 


From: William.Sherman@CH2M.com [mailto:William.Sherman@CH2M.com]
Sent: Thursday, April 09, 2009 2:33 PM
To: seaint@seaint.org
Subject: RE: Cassion Steel Casing check

 

I would say "at rest pressure".  How can a uniformly loaded circular casing deflect to develop active earth pressure?

 

Bill Sherman

CH2M HILL / DEN

720-286-2792

 

 


From: Garner, Robert [mailto:rgarner@moffattnichol.com]
Sent: Thursday, April 09, 2009 2:51 PM
To: seaint@seaint.org
Subject: RE: Cassion Steel Casing check

Active only.

 


From: Dilip Patel [mailto:dp_enco@yahoo.com]
Sent: Thursday, April 09, 2009 1:10 PM
To: seaint@seaint.org
Subject: Cassion Steel Casing check

 

Do you check casing wall for hoop stress under active earth pressure only or you also check under passive earth pressure ?
Caisson is considered similar to tank under pressure, not as a column or sheet pile design.
Any thoughts ?
Thanks.

 

RE: Cassion Steel Casing check

I would say "at rest pressure".  How can a uniformly loaded circular casing deflect to develop active earth pressure?
 
Bill Sherman
CH2M HILL / DEN
720-286-2792
 


From: Garner, Robert [mailto:rgarner@moffattnichol.com]
Sent: Thursday, April 09, 2009 2:51 PM
To: seaint@seaint.org
Subject: RE: Cassion Steel Casing check

Active only.

 


From: Dilip Patel [mailto:dp_enco@yahoo.com]
Sent: Thursday, April 09, 2009 1:10 PM
To: seaint@seaint.org
Subject: Cassion Steel Casing check

 

Do you check casing wall for hoop stress under active earth pressure only or you also check under passive earth pressure ?
Caisson is considered similar to tank under pressure, not as a column or sheet pile design.
Any thoughts ?
Thanks.

 

RE: Cassion Steel Casing check

To clarify, designing underground structures to resist soil pressures is very similar to dancing with a very large woman.  Of course, the male is expected to lead, so the male guides his very large woman partner with his arms and similar body language.  These leading forces, felt in his arms as he guides his partner, are akin to the driving soil forces on, say a retaining wall or underground tank.  These are the active forces which are used to determine how strong our little man must be to guide his large mate.  These active forces are resisted by his muscles (equivalent to the retaining wall rebar).  The mass of his large mate, of course resists these forces, and even if he pushes really hard, her mass will resist the two of them from toppling over.  She represents passive soil forces.  The woman cannot push actively because she is not leading, he is.  However, she sure can resist being pushed over, just like the passive forces in the soil.  Granted this example has our plump partner acting more like a gravity wall, but soil passive forces can be thought of similarly.

 

So if you need some more insight, grab you a very large woman and try a waltz with her.  Try pushing her over and see what happens.  Then think of big pile of dirt resisting your efforts to knock her over.  Now I think you've got it.

 

ps:  It's best not to tell her what you are doing.

 

 

Bob Garner S.E.

 


From: Dilip Patel [mailto:dp_enco@yahoo.com]
Sent: Thursday, April 09, 2009 1:10 PM
To: seaint@seaint.org
Subject: Cassion Steel Casing check

 

Do you check casing wall for hoop stress under active earth pressure only or you also check under passive earth pressure ?
Caisson is considered similar to tank under pressure, not as a column or sheet pile design.
Any thoughts ?
Thanks.

 

RE: Cassion Steel Casing check

Active only.

 


From: Dilip Patel [mailto:dp_enco@yahoo.com]
Sent: Thursday, April 09, 2009 1:10 PM
To: seaint@seaint.org
Subject: Cassion Steel Casing check

 

Do you check casing wall for hoop stress under active earth pressure only or you also check under passive earth pressure ?
Caisson is considered similar to tank under pressure, not as a column or sheet pile design.
Any thoughts ?
Thanks.

 

Cassion Steel Casing check

Do you check casing wall for hoop stress under active earth pressure only or you also check under passive earth pressure ?
Caisson is considered similar to tank under pressure, not as a column or sheet pile design.
Any thoughts ?
Thanks.


Re: Retaining wall footing resultant CBC

As Bill said huge footing
 
Joe Venuti
Johnson & Nielsen Associates
Palm Springs, CA
 
In a message dated 4/9/2009 12:51:27 P.M. Pacific Daylight Time, jeffsmith7@comcast.net writes:
I think the issue came up after his attempt at a wall design with a seismic increment of 18H^2 point load at .6H up the wall ;-)


From: Jnapd@aol.com [mailto:Jnapd@aol.com]
Sent: Thursday, April 09, 2009 12:02 PM
To: seaint@seaint.org
Subject: Re: Retaining wall footing resultant CBC

Jeff
Sounds like your colleague sleeps quite restfully at night due to his conservative approach...not that there is anything wrong with that choice.
 
Joe Venuti
Johnson & Nielsen Associates
Palm Springs, CA
 
In a message dated 4/9/2009 10:31:14 A.M. Pacific Daylight Time, jeffsmith7@comcast.net writes:
The reason I was asking is because the other day an engineering collegue told me he designs to the middle third for retaining walls for non essential facilities.  I wonder if  that was required from an old code requirement or maybe some older soils reports required it?
 
Thanks for your feedback.
 
Jeff


From: Hugh Brooks [mailto:hbap@aol.com]
Sent: Thursday, April 09, 2009 9:49 AM
To: seaint@seaint.org
Subject: RE: Retaining wall footing resultant CBC

This is an arguable issue, but I accept the design if outside middle third if soil pressure OK and stability >1,5.

Hugh

 

From: Jeff Smith [mailto:jeffsmith7@comcast.net]
Sent: Thursday, April 09, 2009 9:44 AM
To: seaint@seaint.org
Subject: Retaining wall footing resultant CBC

 

California Building Code section 1806A.1 requires the resultant must be in the middle half using 1605A.3 load combinations. I don't see this requirement in chapter 1806. For non essential facilities are there any requirements for the retaining wall resultant, or do we just need a 1.5 safety factor?

 

Jeff



Feeling the pinch at the grocery store? Make dinner for $10 or less.


Feeling the pinch at the grocery store? Make dinner for $10 or less.

RE: Retaining wall footing resultant CBC

I think the issue came up after his attempt at a wall design with a seismic increment of 18H^2 point load at .6H up the wall ;-)


From: Jnapd@aol.com [mailto:Jnapd@aol.com]
Sent: Thursday, April 09, 2009 12:02 PM
To: seaint@seaint.org
Subject: Re: Retaining wall footing resultant CBC

Jeff
Sounds like your colleague sleeps quite restfully at night due to his conservative approach...not that there is anything wrong with that choice.
 
Joe Venuti
Johnson & Nielsen Associates
Palm Springs, CA
 
In a message dated 4/9/2009 10:31:14 A.M. Pacific Daylight Time, jeffsmith7@comcast.net writes:
The reason I was asking is because the other day an engineering collegue told me he designs to the middle third for retaining walls for non essential facilities.  I wonder if  that was required from an old code requirement or maybe some older soils reports required it?
 
Thanks for your feedback.
 
Jeff


From: Hugh Brooks [mailto:hbap@aol.com]
Sent: Thursday, April 09, 2009 9:49 AM
To: seaint@seaint.org
Subject: RE: Retaining wall footing resultant CBC

This is an arguable issue, but I accept the design if outside middle third if soil pressure OK and stability >1,5.

Hugh

 

From: Jeff Smith [mailto:jeffsmith7@comcast.net]
Sent: Thursday, April 09, 2009 9:44 AM
To: seaint@seaint.org
Subject: Retaining wall footing resultant CBC

 

California Building Code section 1806A.1 requires the resultant must be in the middle half using 1605A.3 load combinations. I don't see this requirement in chapter 1806. For non essential facilities are there any requirements for the retaining wall resultant, or do we just need a 1.5 safety factor?

 

Jeff



Feeling the pinch at the grocery store? Make dinner for $10 or less.