Tim,
It was discussed earlier in the year. In my experience, in 80% of the projects, 1,000 PSF suffices (as it should), if not - find a geotech familiar with the area to write a memo reflecting the requirements of the 2007 code (another 15%), if not - then a full blown soil report will be required.
V. Steve Gordin, SE
Irvine CA
Irvine CA
----- Original Message -----From: Pinyon EngineeringSent: Monday, July 21, 2008 14:37Subject: Soils ReportsHi,In the new 2007 California Building Code -- section 1802 requiring a soils report for all new projects - even single family homes! what is the reason for this . Do the geotechnical engineers need more work - Were there any spectacular failures I missed that caused this provision?any comments or insightTim RudolphBishop CA