Thursday, July 26, 2007

RE: excavation

That's one hellofa ditch witch.


> > Chris:
> >
> > In California I understand that any excavation 5™-0 deep and deeper
> > needs shoring. I would confirm that with the OSHA documents. I also
> > understand that the fine for not shoring according to code is
> > substantial.
> >
> > Respectfully,
> > Bob Freeman
> > Architect
> > Structural Designer
> > Integrated Design Services, Inc.
> > (949) 387-8500
> >
>
> Hello Bob,
>
> I was told that OSHA was okay with depths greater
> than 5 ft. if the width of trench was twice as wide as
> it is deep. So if this is true and the cost of shoring
> would be much more than the cost of the excavator,
> then wider trenches might be an option.
>
> Take Care,
> Lloyd

******* ****** ******* ******** ******* ******* ******* ***
* Read list FAQ at: http://www.seaint.org/list_FAQ.asp
*
* This email was sent to you via Structural Engineers
* Association of Southern California (SEAOSC) server. To
* subscribe (no fee) or UnSubscribe, please go to:
*
*

http://www.seaint.org/sealist1.asp
*
* Questions to seaint-ad@seaint.org. Remember, any email you
* send to the list is public domain and may be re-posted
* without your permission. Make sure you visit our web
* site at: http://www.seaint.org

******* ****** ****** ****** ******* ****** ****** ********