To All,
  
 I am working on a project where I need to span the floor beams 52 feet and at about half way thru the span the beam changes from being horzontally level to sloping at 1/8 or 1/4 inch per foot, (going from an interior space to an exterior deck). I assume a full pen weld at this transition will work, but are there concerns I am overlooking?
  
 Thanks in Advance,
  
 Larry Hauer, S.E.
 		 	   		  