Re: Old Structural Mesh BF912

That's a tough one to figure out.  Any good leads yet?  I'll check our office library, but it sounds like a proprietary call-out.  My guess is the 9 means a No. 9 wire.  Maybe spaced at 12"o.c.  Good luck with this one.

On Wed, Sep 7, 2011 at 2:25 PM, Martin Li <mli@tb-engr.com> wrote:

All,

 

We are working on a project that involves an existing reinforced concrete building with the drawings dated 1937.  The reinforcing specified for 3" slab over joists is BF912 Mesh.  Does anyone know BF912 Mesh?

 

TIA

 

Martin Li, P.E.




--
David Topete, SE