RE: HIGH CLEAR HEIGHT CONCRETE WALLS

Formwork pressures and stability … I suggest investigation of "slip-form" construction techniques.

 

Thor A. Tandy P.Eng, C.Eng, Struct.Eng, MIStructE
Unit 7 - 625 Hillside Ave
Victoria, BC, V8T 1Z1
Tel/Fax: (250) 382-9115

Alternate: (250) 999-4504
Email:
vicpeng@telus.net

Please consider the environment before printing out this e-mail

 

 

 

From: William Haynes [mailto:gtg740p@gmail.com]
Sent: November-06-11 12:05 PM
To: seaint@seaint.org
Subject: HIGH CLEAR HEIGHT CONCRETE WALLS

 

Can anyone tell me what construction difficulties may be encountered for a building that is around 90 feet clear height using poured concrete? Shipping on precast this long would be an issue and I don't see it practical to create continuity in precast if using stacked modules. I am concerned with the cost of bracing the high poured walls during construction as they are being built and figuring this cost into a preliminary cost estimate.

Will Haynes