Did you have 7 days listed in your concrete specifications? Or just a reference to ACI 301, etc.?
Will Haynes, PE
On 5/17/07, Jim Wilson <wilsonengineers@yahoo.com> wrote:
I have been asked about the need to wait 7 days before placing a concrete wall on a new footing. Is this an enforcable requirement referenced by the code? Or this only a guide and a "proceed at your own risk" situation if placing the wall before receiving 7-day breaks on the footing?And is there a similar requirement that forms cannot be erected on a footing until 3 days after footing placement?Jim Wilson, PEStroudsburg, PA